Question: QUESTION 1 During planning, the team has identified the items in the following table as work to be done on the project. Draw a network

QUESTION 1

During planning, the team has identified the items in the following table as work to be done on the project.

Draw a network diagram to graphically depict this flow.

All relationships are F-S relationships and durations are in days.

TASK DURATION SUCCESSOR A 1 D B 2 E C 4 F D 2 G E 3 I F 4 H G 6 K H 1 J I 5 J J 2 FINISH K 1 FINISH

What is the critical path and duration for this flow and explain how you came to decide this.