Question: Question 1. Given the following information about a project, which activities are on budget, which are over, and which are under budget? Activity A B

Question 1. Given the following information about

Question 1. Given the following information about a project, which activities are on budget, which are over, and which are under budget? Activity A B Progress of the planned work to Critical activity be done Ratio 70% 60% 0.8 80% 100% 1 50% 90% 0.5 30% 60% 0.5 5% 15% 1.5 C D E