Question: QUESTION 1 ______________________________ includes the processes required to acquire goods and services for a project from outside the performing organization. a. Quality management b. Project

QUESTION 1

  1. ______________________________ includes the processes required to acquire goods and services for a project from outside the performing organization.

    a.

    Quality management

    b.

    Project management

    c.

    Project integration management

    d.

    Project procurement management

0.5 points

QUESTION 2

  1. In agile project management _______________ is a short cycle of development, the output is a shippable product functionality and its duration is between one to four weeks.

    a.

    Phase

    b.

    Daily Scrum

    c.

    Sprint

    d.

    Release

0.5 points

QUESTION 3

  1. A staffing management plan often includes a resource ______________, which is a column chart that shows the number of resources assigned to the project over time.

    a.

    Chart

    b.

    Histogram

    c.

    Graph

    d.

    Timeline

0.5 points

QUESTION 4

  1. You purchased a house by investing R.O. 20000 and you sold that house for R.O. 35000 after one year. Find the return on investment (%).

    a.

    25%

    b.

    75%

    c.

    50%

    d.

    100%

0.5 points

QUESTION 5

  1. Which of the following is NOT part of triple constraint of project management?

    a.

    Meeting time goals

    b.

    Meeting cost goals

    c.

    Meeting scope goals

    d.

    Meeting quality goals

0.5 points

QUESTION 6

  1. _______________________________ is a WBS development technique that uses branches radiating from core idea to structure thoughts and ideas.

    a.

    Analogy approach

    b.

    Top-down approach

    c.

    Mind mapping

    d.

    Bottom up approach

0.5 points

QUESTION 7

  1. In the context of Project Quality Management, a Pareto chart is a _________________ tool.

    a.

    Quality Planning

    b.

    Quality Control output

    c.

    Quality Assurance

    d.

    Quality control

0.5 points

QUESTION 8

  1. _________________________ can be directly related to creating the products and services of the project.

    a.

    Indirect cost

    b.

    Cost variance

    c.

    Sunk cost

    d.

    Direct cost

0.5 points

QUESTION 9

  1. A person needs are acquired or learned over time and shaped by their life experience, to which of the following motivation theories this statement is related?

    a.

    Maslows theory

    b.

    McGregors Theory

    c.

    McClelland Acquired-need theory

    d.

    Thamhain and Wilemons influences and power

0.5 points

QUESTION 10

  1. You are engaged in gathering information from stakeholders to determine whose interests should be taken into account throughout the project. This is called ______________________.

    a.

    Plan stakeholder management

    b.

    Identify stakeholders

    c.

    Expert judgment

    d.

    Stakeholder analysis

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!