Question: Question 1 : Labour Productivity A company is considering two locations for manufacturing its products: Location X and Location Y . The labour costs and

Question 1: Labour Productivity
A company is considering two locations for manufacturing its products: Location X and Location Y. The labour costs and production capacities at each location differ. Below are the details for each location:
Location X:
Labour cost per day: $224
Hours required per unit: 40
Maximum production capacity: 1,000 units per month Location Y:
Labour cost per hour: $280
Hours required per unit: 70
Maximum production capacity: 1,200 units per month
Question 1-1
Calculate the labour cost per unit for each location.
Question 1-2
Note: this answer does not require a calculation but an analysis of the information.
If the company plans to produce 900 units per month, which location should they choose based on labour cost per unit?
Question 1-3
Note: this answer does not require a calculation but an analysis of the information.
If the company plans to increase production to 1,100 units per month, which location is the better option considering both labour costs per unit and productivity capacity?
A ocal emtrepreneur wants to upenn a volne manuracturng piant with a warehouse in Prince Edward County to supply the warehouses in the county most efficiently. Using the centre of gravity method, where should this manufacturer/warehouse be located?
\table[[,X,Y,Projected # of Cases of Bottles/per month],[Vineyards,18,18.5,24],[Three Dog Winery,23,9,17],[Waupoos Estates Winery,23,8,10],[Black Prince Winery,17,12,37],[Huff Estate Winery,12,10.5,12],[TerraCello Winery,11,9,18],[Karlo Estates,9.5,4.5,29],[Sandbanks Winery,7.5,3.5,16],[Casa-Dea Winery,6.5,4,9],[Traynor Family Vinyard,7,6,34],[Closson Chase Vineyards 8.5,7.5,,]]
Calculate the X and Y co-ordinates to 1-decimal place.
Question 3: Staffing & Balancing Work Cells
A manufacturing facility produces 500 units of a product in an 8-hour shift. The total available time for production in 7.5 hours when accounting for breaks. If the total cycle time to produce one unit is 5 minutes, calculate the takt-time and then determine the number of workers needed to staff the work cell to meet the production demand.
Question 3-1 Takt Time
Calculate takt-time in seconds per unit
Question 3-2 Workers Needed
Calculate the number of workers needed in the work cell.
Question 4: Time Studies
A time study was conducted on a particular task performed by an operator in a manufacturing plant. The allowance factor is 15%. The following times, in seconds, were recorded for ten cycles of the task:
32,30,3,34,33,29,35,31,30,32
Question 7: Reliability with Redundancies
As VP of operations at Normoyle Engineering, you must decide which product design, design A or design B , has the higher reliability. B is designed with backup units for components R3 and R4. What is the reliability of each design?
Question 7-1
What is the reliability for Design A?
Design A
R1,R2,R3,R4
0.990.950.9980.995
Question 7-2
What is the reliability for Design B?
Design B
R1,R2,R3,R4
0.990.950.950.99
0.950.99
Question 7-3
Which design is better?
Question 8: Decision Tree
A company is developing a new product and has two design options to consider:
Design Option A: A simpler, less innovative product design that costs $2 million to develop. There is a 70% chance that the product will perform well in the market, leading to profits of $6 million. If the product performs poorly (30% chance), it will generate profits of only $1 million.
Design Option B: A more complex, highly innovative product design that costs $4 million to develop. If the product performs well (60% chance), it will yield profits of $12 million. If it performs poorly (40% chance), it will generate profits of $2 million.
Question 8-1 Design Option A
Calculate the expected monetary value (EMV) for Design Option A.
Question 8-2 Design Option B
Calculate the expected monetary value (EMV) for Design Option B.
Question 8-3
Based on the expected monetary value (EMV), which design option should the company choose?
Question 9: Upload your Excel document!
 Question 1: Labour Productivity A company is considering two locations for

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!