Question: Question 1 Most optimistic likely Pessimistic Expected Variance m b Timet o 1 2 9 6 7 8 a Activity Predecessors A B A 6

Question 1 Most optimistic likely Pessimistic
Question 1 Most optimistic likely Pessimistic Expected Variance m b Timet o 1 2 9 6 7 8 a Activity Predecessors A B A 6 A 2 BC 2 5 8 B.D E 2 3 4 Construct the project Network Find the expected duration and Variance of each activity Find the critical path CPM and expected project completion time CP and slake time ST What is the probability of completion the project on or before 23 weeks? ta DC to te ob OC od CP CPM st value of FROM standard normal distribution table

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!