Question: QUESTION : 1 outside the critical path. d ) What is the probability of completing the project in 5 3 days? What is the probability

QUESTION : 1 outside the critical path.
d) What is the probability of completing the project in 53 days? What is the probability of completing this project in 48
days?
Question 2
The total budgeted cost (PV) for each of the 15 work packages that make up a project is shown in the table below. The
percentage of work actually completed for each work package, as well as the cumulative PV and actual cost (AC) for each
work package, at a particular review point, are also provided in the table.
a) Compute the schedule variance (SV), cost variance (CV), schedule-performance index (SPI) and cost-
performance index (CPI) for this work package.
b) Compute the 'estimate at completion' using two of the three formulae introduced in the subject. Succinctly state
any conditions (or the rationale) underpinning each of the two formulae used.
c) Identify two practical situations in which each of the above formulae would be preferred?
 QUESTION : 1 outside the critical path. d) What is the

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!