Question: QUESTION : 1 outside the critical path. d ) What is the probability of completing the project in 5 3 days? What is the probability
QUESTION : outside the critical path.
d What is the probability of completing the project in days? What is the probability of completing this project in
days?
Question
The total budgeted cost PV for each of the work packages that make up a project is shown in the table below. The
percentage of work actually completed for each work package, as well as the cumulative PV and actual cost AC for each
work package, at a particular review point, are also provided in the table.
a Compute the schedule variance SV cost variance CV scheduleperformance index SPI and cost
performance index CPI for this work package.
b Compute the 'estimate at completion' using two of the three formulae introduced in the subject. Succinctly state
any conditions or the rationale underpinning each of the two formulae used.
c Identify two practical situations in which each of the above formulae would be preferred?
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
