Question: QUESTION 1 QUESTION 1 Activity Preceeding Activity Time ES EF LS LF A - 6 0 6 42 48 B - 18 0 18 0
QUESTION 1
-
QUESTION 1
Activity
Preceeding Activity
Time
ES
EF
LS
LF
A
-
6
0
6
42
48
B
-
18
0
18
0
18
C
-
4
0
4
30
34
D
B
30
18
48
18
48
E
A,D
4
48
52
48
52
F
C
18
4
22
34
52
G
E,F
24
52
76
52
76
1. Which of the statements is true about activity F:
A. Maximum number of days required to complete activity F without delaying the project is 52 days
B. Activity F is on the critical path
C. Activity F cannot be started unless activities A, B, C, D, and E are completed.
D. Activity F must be started by day 4 in order not to delay the project
4 points
QUESTION 2
What is the slack time for activity C:
4 points
QUESTION 3
Till what day a manager can wait to complete the activity C so that he will not delay the completion of the project?
A. 2
B. 34
C. 0
D. 24
4 points
QUESTION 4
1. What is the minimum number of days by which this project can be completed:
A. 32
B. 76
C. 54
D. 22
4 points
QUESTION 5
The activities that constitute the critical path are:
ADEG
BGH
None of the above.
BDEG
4 points
QUESTION 6
The Critical Path is:
The chain of activities through the Network diagram which includes the greatest slack
None of the answers are correct
The chain of activities through the Network diagram which includes as many different activities as possible
The chain of activities through the Network diagram which includes no slack
4 points
QUESTION 7
The latest completion time is:
latest starting time + slack
None of the answers are correct
earliest starting time + slack
Earliest completion time + slack