Question: QUESTION 1 QUESTION 1 Activity Preceeding Activity Time ES EF LS LF A - 6 0 6 42 48 B - 18 0 18 0

QUESTION 1

  1. QUESTION 1

    Activity

    Preceeding Activity

    Time

    ES

    EF

    LS

    LF

    A

    -

    6

    0

    6

    42

    48

    B

    -

    18

    0

    18

    0

    18

    C

    -

    4

    0

    4

    30

    34

    D

    B

    30

    18

    48

    18

    48

    E

    A,D

    4

    48

    52

    48

    52

    F

    C

    18

    4

    22

    34

    52

    G

    E,F

    24

    52

    76

    52

    76

    1. Which of the statements is true about activity F:

    A.

    Maximum number of days required to complete activity F without delaying the project is 52 days

    B.

    Activity F is on the critical path

    C.

    Activity F cannot be started unless activities A, B, C, D, and E are completed.

    D.

    Activity F must be started by day 4 in order not to delay the project

    4 points

    QUESTION 2

    What is the slack time for activity C:

    4 points

    QUESTION 3

    Till what day a manager can wait to complete the activity C so that he will not delay the completion of the project?

    A.

    2

    B.

    34

    C.

    0

    D.

    24

    4 points

    QUESTION 4

    1. What is the minimum number of days by which this project can be completed:

    A.

    32

    B.

    76

    C.

    54

    D.

    22

    4 points

    QUESTION 5

    The activities that constitute the critical path are:

    ADEG

    BGH

    None of the above.

    BDEG

    4 points

    QUESTION 6

    The Critical Path is:

    The chain of activities through the Network diagram which includes the greatest slack

    None of the answers are correct

    The chain of activities through the Network diagram which includes as many different activities as possible

    The chain of activities through the Network diagram which includes no slack

    4 points

    QUESTION 7

    The latest completion time is:

    latest starting time + slack

    None of the answers are correct

    earliest starting time + slack

    Earliest completion time + slack

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!