Question: Question 1: Question 2: The Precedence Diagramming Method (PDM) is a network diagramming technique in which activities are represented by arrows and connected at points

Question 1:

Question 1: Question 2: The Precedence

Question 2:

Question 1: Question 2: The Precedence

The Precedence Diagramming Method (PDM) is a network diagramming technique in which activities are represented by arrows and connected at points called nodes. True False The cost performance index (CPI) is: The earned value minus the actual cost. An estimate of what it will cost to complete the project based on performance to date. The ratio of actual cost to earned value. The ratio of earned value to actual cost