Question: Question 1 Real Ltd. has been asked to submit a bid on two prospective jobs, one for Fake Racing a rally team from Trinidad and

Question 1

Real Ltd. has been asked to submit a bid on two prospective jobs, one for Fake Racing a rally team from Trinidad and the other for Hoax Racing of Barbados. The company uses a job costing system and applies overheads using machine hours. Total overhead for the year is expected to be $450 000, and it is expected that 50, 000 machine hours will be worked.

Addition information relating to the prospective jobs is as follows:

Fake Racing

Hoax Racing

Direct materials

$7 500

$10 000

Direct labour

$13 000

$12 500

Number of inspections

4

2

Number of set-ups

3

1

Number of machine hours

2 000

4 500

Number of engineering hours

130

50

  1. Using the traditional job costing system, calculate the total cost of each job. Show the calculation of the OAR. (7 marks)

Real Ltd is concerned that the company may be over-or-under-pricing the jobs on which they bid. The company has decided to use activity based costing to estimate the cost of future jobs. Real Ltd has assembled the following information:

Costs ($)

Cost driver

Total Capacity

Machining

200 000

Machine hours

50 000 machine hrs

Set-up

35 000

No. of set-ups

200 set-ups

Engineering

125 000

No. of engineering hours

6 250 engineering hrs

Inspection

90 000

No. of inspections

7 500 inspections

Total Cost

450 000

B. Compute the activity rate for each activity. (6 marks)

C. Compute the total cost of each job using activity based costing. (12 marks)

(Total 25 marks)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Accounting Questions!