Question: QUESTION 1 Requested daily quantity for a product is 3 7 5 units ( defect free ) . The production times ( given as normal
QUESTION
Requested daily quantity for a product is units defect free The production times given as normal time of the three operations respectively are as follows: Operation min; Operation min; and Operation min. The defect rates is given as ;; for each station in serial. Workers assigned to these operations will accomplish the conversions. The number of workers in the department is limited to There are two scenarios:
Scenario I: With Rework
Although the defect rates are given, no product is permitted to leave the plant with any quality defects. Accordingly, all of the defects must be corrected, and the average time to correct the defect is of the initial conversion time Example for min repair of min The same work teams will accomplish this rework. The plant is run as a oneshift day meal break of min unpaid; Short Breaks min; downtime min operation. Don't forget: The number of workers in the department is limited to The performance of employees Performance because of qualified workforce and motivational effect of wage support A performance below or above is not desired in determining the required number of workers.
Fill the table below.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock