Question: QUESTION 1 Study the following project - spending plan in Question 2 and calculate the following ( indicate the actual calculations in full ) :

QUESTION 1
Study the following project-spending plan in Question 2 and calculate the following (indicate the
actual calculations in full):
1. Cash Flow for Task b
2. Total BCWP
3. CVAR/CV for Task a
4. BCWP - ACWP for Task c
5. BCWP for Task d
6. Total ACWP
7. Total CVAR/CV
8. Total BCWP Total cash flow
QUESTION 2
Re-draw the project spending plan and fill-in the missing values.
PROJECT SPENDING PLAN
PROJECT NAME : HOSTING OF THE LAUNCH OF A COMMUNITY
CITIZEN PARTICIPATION FORUM IN CARLETONVILLE
FROM 1014 JUNE 2024
START DATE : 3 MARCH 2024
PROJECT DURATION : 5 MONTHS
CURRENT DATE : 3 FEBRUARY 2024
CURRENT PROJECT BUDGET : R300000
ACTIVITY/TAS
K
COMPLETIO
N DATE
SCHEDULE
D
BUDGETE
D AMOUNT
(BCWP)
CASH
FLOW
ACTUAL
COST
(ACWP)
COST
VARIANCE
(CVAR/CV)
Task a 31/3/2024 R87000.00??? R93000-R6000
Task b 30/4/2024??? R48000 R48000-R3000
Task c 30/5/2024 R78000??? R78000???
Task d 30/6/2024 R90000 R84000??? R6000
TOTAL 30/7/2024????????????
QUESTION 3
Based on the outcome of your above calculations, draw the five (5) S-Curves for the individual 4
Tasks a d as well as the total Projects CVAR (sum of all 4 tasks) on a diagram. A hand-drawn
diagram will suffice. Remember to state if it is negative or positive. In the discussion and analysis of
the diagram, list the reasons why it is negative or positive. See Section 2.1 and Figure 4.1 in Unit 4
of the Study Guide.
Lastly, you need to also reflect on what you have learnt in doing this cost analysis exercise

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!