Question: Question 1 Suppose that an operations manager is trying to determine what forecasting method to use for the following forecasting problem. Based on the following
Question
Suppose that an operations manager is trying to determine what forecasting method to use for the following forecasting problem. Based on the following historical data, calculate the following forecasts and specify which forecasting method you would utilize.
Actual
Month Demand
We can calculate the weighted month forecasts using weights of and for periods In particular, the forecast for period is
Question options:
Question
Refer to the information in Q
We can calculate the double exponential smoothing forecasts for periods using an initial trend forecast T of and initial exponential smoothing forecast S of an of and a of
In particular, the forecast for period is
Question options:
Question
Refer to your calculations in Q and Q
Calculate the Mean Absolute Deviation MAD over periods and by the above each technique. Which forecasting method is better in terms of MAD performance measure?
Question options:
double exponential smoothing method
weighted month moving average method
Question
An operations manager has just finished the reviewing of the latest draft of an upcoming project. The following table provides information about the normal time for each activity, activity sequence and information about crashing costs to shorten some of the activities. He is concerned about the project duration and expects the owners will want the project shortened. For each activity, the maximal number of weeks available for crashing is two weeks. Each activity in the st column precedes the corresponding activityactivities in the nd column.
Activity: Start, a b c d e f g h i j k l m n o p q r s t u v x y z
Precedes: a b c d d e f g h end, end
Normal Timewk:
Crashing First Week:
Costs in $ Second Week:
What is the current project duration assuming the project is not shortened?
Question options:
Question
Refer to the information in Q
The operations manager thinks the owners may ask him to shorten the project by up to four weeks. Therefore, prepare the lowest cost crashing plan that will reduce the project duration by four weeks.
Question :
hhfa
hhac
hfac
hhfc
Question
Refer to the information in Q
Suppose that the indirect cost is $week for this project. In order to minimize the total cost of indirect cost and the crashing cost over the whole project duration, how many weeks will be reduced regarding the project duration?
Question options:
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
