Question: Question 1. Task Mean Completion Time St. Dev A 4 0.6 B 5 0.2 E 2 0.1 F 6 1 H 2 0.2 M 6

Question 1.

Task Mean Completion Time St. Dev
A 4 0.6
B 5 0.2
E 2 0.1
F 6 1
H 2 0.2
M 6 0.1

Part 1: The above task gives the mean completion time of each task (in days) and the standard deviation. Based on this information, with 99% probability, in how many days will the project be completed?

A. 25

B. 26.5

C. 27.81

D. 28.32

Part 2: The above task gives the mean completion time of each task (in days) and the standard deviation. Based on this information, what is the probability that the project will be completed in 23 days or less?

A. Less than 5% but more than 3%

B. Less than 3%

C. More than 5% but less than 10%

D. More than 10%

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!