Question: Question 1 : The construction plan for a single house in a 2 1 - house project is as follows. All durations are in weeks.
Question :
The construction plan for a single house in a house
project is as follows. All durations are in weeks. The
deadline to complete all houses is weeks. Determine
the proper crews to use. Before the start of construction,
you found out that you must use one less crew in task B
and two less in task F Also, you get instructions to utilize
double the crews in task E for the last houses only. Draw
the LOB chart that reflects the project with these changes. What will be the project duration?