Question: Question 1 The following table provides information on a project consisting of 11 activities, their duration and any predecessor activities. Activity Duration Immediate predecessor A

Question 1 The following table provides

Question 1 The following table provides information on a project consisting of 11 activities, their duration and any predecessor activities. Activity Duration Immediate predecessor A 3 B 2 A 4 A D 3 E 3 B F 2 G 4 D H 5 E 1 3 F J 4 G 2 H,1,J NB. The Early Start of Activity A is DAY 1. a. Draw the activity network for this project b. Identify the critical path c. How long will it take to complete the project? d. Determine the Early Start of activity D e. Determine the Late Finish of activity J f. What is the float time for activity E? [5 marks] [5 marks] [4 marks] [2 marks] [2 marks] [2 marks]

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!