Question: Question 1 . The setup time for a machine is 3 0 minutes and the processing time is 5 minutes. The parts produced by this

Question 1. The setup time for a machine is 30 minutes and the processing time is 5 minutes. The parts produced by this machine are used in an assembly process that has a capacity of 8 units per hour.
a. If the batch size is 6, what is the capacity of the process?
b. If the batch size is 30, what is the capacity of the process?
Question 2. What is the optimal assignment of the following jobs?
\table[[,Machine,],[,,A,B,C,D],[Job,1,3,9,9,1],[2,6,8,8,10],[3,5,3,8,3],[4,2,1,6,9]]
 Question 1. The setup time for a machine is 30 minutes