Question: Question 1. The setup time for a machine is 30 minutes and the processing time is 5 minutes. The parts produced by this machine are
Question 1. The setup time for a machine is 30 minutes and the processing time is 5 minutes. The parts produced by this machine are used in an assembly process that has a capacity of 8 units per hour.
- If the batch size is 6, what is the capacity of the process?
- If the batch size is 30, what is the capacity of the process?
Question 2. What is the optimal assignment of the following jobs?

\begin{tabular}{|c|cccc|} \multicolumn{1}{c}{} & \multicolumn{4}{c}{ Machine } \\ \cline { 2 - 5 } \multicolumn{1}{c|}{} & A & B & C & D \\ \hline Job & 3 & 9 & 9 & 1 \\ 2 & 6 & 8 & 8 & 10 \\ 3 & 5 & 3 & 8 & 3 \\ 4 & 2 & 1 & 6 & 9 \end{tabular}