Question: Question 1: Using the given table draw the Precedence network of the project ie the Activity on Node Network to find the critical path. .

Question 1: Using the given table draw the Precedence network of the project ie the Activity on Node Network to find the critical path. . For each node mention the earliest start and finish dates For each node mention the latest start and finish dates For each node mention the Float For each node measure the duration For each node measure the span Calculate the Critical path Determine the planned duration of the project Identify the critical tasks and their duration Identify the non-critical tasks and their float. Tasks Duration Days Predecessors 5 B 10 A 20 B D 10 B E 30 F 40 CD 25 E G H 10 E I 35 H J 20 K 5 K L 5 M 15