Question: Question 1: Weighted Factor Scoring Calculate the rating for Project A and for Project B (fill the last column of each table), and make your
Question 1: Weighted Factor Scoring
Calculate the rating for Project A and for Project B (fill the last column of each table), and make your suggestion.
Table 1 - Project A
| Criterion | Criterion Interval Values | Rating | |||||
| Weight | 1 | 0.8 | 0.6 | 0.4 | 0.2 | ||
| Very Good | Good | Medium | Poor | Very Poor | |||
| Use of available personnel | 0.15 |
| X |
|
|
|
|
| Growth Potential | 0.20 |
|
| X |
|
|
|
| Profitability | 0.30 |
| X |
|
|
|
|
| Competitive Advantage | 0.05 |
|
|
| X |
|
|
| Consistence with Technical Competence | 0.20 | X |
|
|
|
|
|
| Compatibility with Existing Project | 0.10 |
| X |
|
|
|
|
| Sum | 1.00 | Project Score: |
| ||||
Table 2 - Project B
| Criterion | Criterion Interval Values | Rating | |||||
| Weight | 1 | 0.8 | 0.6 | 0.4 | 0.2 | ||
| Very Good | Good | Medium | Poor | Very Poor | |||
| Use of available personnel | 0.15 | X |
|
|
|
|
|
| Growth Potential | 0.20 |
| X |
|
|
|
|
| Profitability | 0.30 |
|
| X |
|
|
|
| Competitive Advantage | 0.05 |
| X |
|
|
|
|
| Consistence with Technical Competence | 0.20 |
|
| X |
|
|
|
| Compatibility with Existing Project | 0.10 | X |
|
|
|
|
|
| Sum | 1.00 | Project Score: |
| ||||
Suggestion:
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts