Question: Question 1 What are the two project scheduling techniques? Question 1 options: CPM and PERT WBS and Critical path Cost and Budget Schedule and Cost
Question 1
What are the two project scheduling techniques?
Question 1 options:
CPM and PERT | |
WBS and Critical path | |
Cost and Budget | |
Schedule and Cost |
Question 2
WBS represents the project scope in the form of a hierarchy of
Question 2 options:
Project Management | |
Project Scope | |
Project Deliverables | |
Project Plan |
Question 3
What will be developed by the organization which fits within the existing organization and its strategy?
Question 3 options:
Project Plan Management | |
Project Scope Statement | |
Project Management Tool | |
Project Charter |
Question 4
An appropriate example of a top-down process is summary budget which is developed during the planning process
Question 4 options:
| True | |
| False |
Question 5
As part of project scheduling, the project manager also evaluates other aspects of the
Question 5 options:
Time or Scope | |
Cost or Scope | |
Schedule or Time |
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
