Question: Question 1 What is the EAC for this project, and what does it represent? PV = $2,200, EV - $2,000, AC - $2,500, BAG -

Question 1 What is the EAC for this project, and
Question 1 What is the EAC for this project, and what does it represent? PV = $2,200, EV - $2,000, AC - $2,500, BAG - $10,000 512.500: the revised estimate for total project cost (based on performance thus far) $10,000: the revised estimate for total project cost (based on performance thus far) 512.500; the original project budget $10,000: the original project budget