Question: Question 1 : Work Breakdown structure: Task A , duration 6 , dependent on none Task B , duration 5 , dependent on none Task

"Question 1:
Work Breakdown structure:
Task A, duration 6, dependent on none
Task B, duration 5, dependent on none
Task XE08 C, duration 3, dependent on none
Task D, duration 12, dependent on task B and task C
Task E, duration 2, dependent on task A
Task F, duration 5, dependent on task B
Task G, duration 1, dependent on task B
Task H, duration 9, dependent on task E and task F
Task I, duration 7, dependent on task G
Task J, duration 7, dependent on task H
Task K, duration 3, dependent on task I
Task L, duration 5, dependent on task D
a.(15) Create an Activity-on-Arrow (AOA) diagram based on the given work
breakdown structure in the above.
b.(15) Calculate ES, EF, LS, and LF for each task and the amount of slack. List the tasks
that appear on the critical path"

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Programming Questions!