Question: Create an Activity-on-Arrow (AOA) diagram based on the following information: Task A, duration 6, dependent on none Task B, duration 5, dependent on none Task
Task A, duration 6, dependent on none
Task B, duration 5, dependent on none
Task C, duration 3, dependent on none
Task D, duration 12, dependent on task B and task C
Task E, duration 2, dependent on task A
Task F, duration 5, dependent on task B
Task G, duration 1, dependent on task B
Task H, duration 9, dependent on task E and task F
Task I, duration 7, dependent on task G
Task J, duration 7, dependent on task H
Task K, duration 3, dependent on task I
Task L, duration 5, dependent on task D