Question: Question 1 You have signed a contract to build a new parking lot for a park. You will receive a RM500 bonus for completing the

Question 1 You have signed a contract to build a

Question 1 You have signed a contract to build a new parking lot for a park. You will receive a RM500 bonus for completing the project within 14 days. The contract also contains a penalty clause in which you will lose RM150 for each day the project takes longer than 14 days. ID Table 1: Network Information of park's Parking Lot Description Predecessor Time A Pour foundation None 3 B Erect frame A 3 Roof B 4 D Windows B 1 E Doors B 1 F Electrical B 3 G Rough-in frame C,D,E,F 2 H Door opener EE 1 1 Paint GH 2 J Cleanup I 1 Consider forward and backward pass, calculate how many days will the project takes. Do you expect to receive a bonus or penalty? Determine its critical path (10 Marks)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!