Question: Question 1 Your answer should based on the following table below: Activity Duration Estimate (Week) Immediate Predecessor Responsible Person A 4 - AK B 2

Question 1

Your answer should based on the following table below:

Activity

Duration Estimate (Week)

Immediate Predecessor

Responsible Person

A

4

-

AK

B

2

-

AK

C

3

A

DJ

D

5

A

DJ

E

8

B

DF

F

8

C

DIN

G

6

D,E

AYU

H

9

F

AMY

I

10

G

SONIA

J

4

H,I

MAN

  1. Draw a network diagram, calculate the Earliest Start (ES), Earliest Finish (EF), or Latest Start (LS), Latest Finish (LF) times for each activity using the AIB (Activity In The Box) format.

  1. Analyse and show which activity (s):

  1. Has positive slack time
  2. Has negative slack time
  3. Identify the critical paths. Calculate the total project duration

Question 2

Your answer should based on the following table below:

Activity

Duration Estimate (Days)

Immediate Predecessor

Responsible Person

A

15

-

John

B

24

A

Aleeya

C

33

A

Aleeya

D

20

B,C

Ben

E

10

D

Lily

F

10

E

Cynthia

G

28

F

Jefry

H

22

F

Jefry

I

15

G,H

Rizqi

  1. Draw the network diagram, show and calculate either the Earliest Start (ES) or Earliest Finish (EF) or Latest Start (LS) or Latest Finish (LF) times for each activity using the Activity In The Box (AIB) format.

  1. Identify the critical path and the number of days needed to complete the project

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!