Question: Question 10 0.5 The calculated total float of a project activity is 4 days. Which means This activity lies in the critical path of the

Question 10 0.5 The calculated total float of a

Question 10 0.5 The calculated total float of a project activity is 4 days. Which means This activity lies in the critical path of the project because of non-zero float O This activity is 4 days behind the planned end date This activity can be delayed by upto 4 days without delaying the project end time This activity is completed 4 days ahead of the planned end date Previous Not saved Submit