Question: > Question 10 10 pts n a project management problem after employing CPM it was found that A-C-D-E-F-G-H is the critical path. The times of

> Question 10 10 pts n a project management

> Question 10 10 pts n a project management problem after employing CPM it was found that A-C-D-E-F-G-H is the critical path. The times of completing activities E, F, G and Hare respectively 16, 14, 10 and 24 days. If ES (early start time) of E is 18, what is the late finish time) LF of H