Question: Question 10 (12 points) Listen Complete the MRP schedule for A-G, given the following information Safety Stock , Lead time 2 weeks, EOQ 45 Period

Question 10 (12 points) Listen Complete the MRP
Question 10 (12 points) Listen Complete the MRP schedule for A-G, given the following information Safety Stock , Lead time 2 weeks, EOQ 45 Period 1 2 3 5 Gross Requirements 25 31 11 20 15 Scheduled Receipts Projected Available Balance 35 C G Net Requirements D Planned Order Receipts E Planned Order Release B A = 6. B-47. C-40. D-10. E-46. F-20. G= 5 A. 4. B=43, 6-41. D-9. E=47. F=18. G= 5