Question: when completing a MRP schedule you are given the following information. safety stock 0 , lead time 2 weeks, EOQ 5 0 period / 1

when completing a MRP schedule you are given the following information.
safety stock 0, lead time 2 weeks, EOQ 50
period /1/2/3/4/5
gross req /25/31/11/20/15
if you use data from months 1-6 to obtain the regression line y=60x+8, what is your forecast for period 4?