Question: Question 10 (3 points) If you are given the Optimistic and Pessimistic values only (in a PERT 3-point estimate), then which of the following will
Question 10 (3 points)
If you are given the Optimistic and Pessimistic values only (in a PERT 3-point estimate), then which of the following will you be able to compute
Question 10 options:
|
| The expected duration |
|
| The standard deviation only |
|
| The standard deviation and the variance |
|
| None of the above |
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts