Question: QUESTION 10 A simple project consists of three consecutive activities as presented in the following Table. Planned Duration Activity A 2 days Activity B Activity

QUESTION 10 A simple project consists of three

QUESTION 10 A simple project consists of three consecutive activities as presented in the following Table. Planned Duration Activity A 2 days Activity B Activity C 1 day 3 days At the end of day 3, an EVA review established the project's planned value, earned value and actual cost as given in the figure and CPI equal to 0.86. 3,200 Planned Value (Cost or Value) 1,700 1,550 Actual Costs Earned Value 0 1 2 3 4 5 6 7 Time Assuming constant cost performance, define the estimated total cost variance (in ) for the project (1 decimal point)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!