Question: A construct project consists of 1 5 activities. Using the CPM method, the following table has been inferred, which represents the duration, earliest start, and

A construct project consists of 15 activities. Using the CPM method, the following table has
been inferred, which represents the duration, earliest start, and latest start of each activity. (20
pts)
Direct cost is assumed to be linearly proportional to the duration of each activity according to
the following relationship:
Direct Cost =$2,000 Duration
a) Complete the table by adding the direct cost column.
b) Calculate the direct-cost outflow for each day based on both earliest and latest start days and
report the results in a table. (Please include the bar charts for both earliest and latest start days
too)
c) Plot the direct-cost outflow diagram per days for both earliest and latest start days.
d) Assume that contractor's bid is $220,000, the overhead cost is $500 per day (should be added
to the direct-costs calculated in step b), and each week has 5 working days. Taking the earliest
start day as the reference, if the contractor is paid uniformly in four installments on a biweekly
basis (starting from day 0), draw a diagram showing both total cost (outflow) and inflow.
e) At day 20, is the balance positive or negative? At this day, what are the percentages of total
outflow and inflow?
***SHOW ALL CALCULATIONS , TABLES, GRAPHS, & DIAGRAMS***
A construct project consists of 1 5 activities.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Civil Engineering Questions!