Question: A construct project consists of 1 5 activities. Using the CPM method, the following table has been inferred, which represents the duration, earliest start, and
A construct project consists of activities. Using the CPM method, the following table has
been inferred, which represents the duration, earliest start, and latest start of each activity.
pts
Direct cost is assumed to be linearly proportional to the duration of each activity according to
the following relationship:
Direct Cost $ Duration
a Complete the table by adding the direct cost column.
b Calculate the directcost outflow for each day based on both earliest and latest start days and
report the results in a table. Please include the bar charts for both earliest and latest start days
too
c Plot the directcost outflow diagram per days for both earliest and latest start days.
d Assume that contractor's bid is $ the overhead cost is $ per day should be added
to the directcosts calculated in step and each week has working days. Taking the earliest
start day as the reference, if the contractor is paid uniformly in four installments on a biweekly
basis starting from day draw a diagram showing both total cost outflow and inflow.
e At day is the balance positive or negative? At this day, what are the percentages of total
outflow and inflow?
SHOW ALL CALCULATIONS TABLES, GRAPHS, & DIAGRAMS
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock