Question: Question 10 Milford Manufactures is trying to develop its master schedule for the next 8 weeks. Below, you will find the forecasted values for Weeks

Question 10 Milford Manufactures is trying to

Question 10 Milford Manufactures is trying to develop its master schedule for the next 8 weeks. Below, you will find the forecasted values for Weeks 1 through 8 and the actual customer orders for Weeks 1 through 4. 1 2 Forecast 150 150 Customer Orders 125 130 90 The on-hand inventory for Week 1 is 30 units and the MPS lot size is 190 units. 110 Week O 160 3 150 145 O 180 4 5 6 7 150 140 140 160 160 Given the information provided above, what would be the projected on-hand inventory for Week 4? 1 pts 8 160