Question: QUESTION 10 points Save Answer Each Unit of end product X requires 3 units of sub- component Z. Complete the following MRP record to answer

 QUESTION 10 points Save Answer Each Unit of end product X

QUESTION 10 points Save Answer Each Unit of end product X requires 3 units of sub- component Z. Complete the following MRP record to answer the next question. ITEM: X, Lead Time:1 week, Order Quantity for item X = Lot for lot Week # 1 2 3 4 5 Gross 35 40 35 15 30 Requirement Schedule Receipts 50 On Hand 40 Net Requirement Plan Order Receipts Plan Order Release For the item X, the net requirement for the period 5 is: O 25 O Zero O 30 None of listed answers are correct