Question: Question 10 What do we know about a job for which the Critical Ratio is less than 1.0? It is running behind schedule It will

Question 10 What do we know about a job for which
Question 10 What do we know about a job for which the Critical Ratio is less than 1.0? It is running behind schedule It will not be done in time It is the lowest priority job at this work center Both its tardiness and its lateness will be greater than 0