Question: Question 105 & 106.) This is Time Study Worksheet from a manufacturing facility. Element TotalCycles Average Time 9 R Normal Time Frequency Unit Normal Time

Question 105 & 106.) This is Time Study Worksheet

Question 105 & 106.) This is Time Study Worksheet from a manufacturing facility. Element TotalCycles Average Time 9 R Normal Time Frequency Unit Normal Time Load and clamp 100 E 0.22 0.23 0.21 0.22 0.22 Run machine E 0.52 0.52 0.52 0.52 0.52 Unload and put aside E 0.12 0.12 0.12 0.13 0.11 105.) Is this snapback time study or continuous time study? Please explain why. 106.) Please determine Standard Minutes (Minutes per Unit) and Unit per Hour. Assume 10% allowance