Question: Question 11 6.67pts In a 0-1 integer programming model, if the constraint x_(1)-x_(2) , it means if project 2 is selected, project 1 . Choose
Question 11
6.67ptsIn a 0-1 integer programming model, if the constraint
x_(1)-x_(2), it means if project 2 is selected, project 1 . Choose the option below that best represents the empty space above. must be selected must not be selected None of the above