Question: Question 8 In a 0 - 1 integer programming model, if the constraint x 2 + x 3 1 . It means that if project

Question 8
In a 0-1 integer programming model, if the constraint x2+x31.
It means that if project 2 is not selected, project 3q,
Choose the option below that best represents the empty sijace above.
will not be selected
will be selected
will always be selected
is more likely to be selected
None of the above