Question: QUESTION 11 A production line is to be designed for a job with three tasks. The task times are .3 minutes, 1.4 minutes, and .7
QUESTION 11
-
A production line is to be designed for a job with three tasks. The task times are .3 minutes, 1.4 minutes, and .7 minutes. For a single production line with no parallel activities, the minimum cycle time in minutes is:
.3.
.7.
1.4.
2.4.
.8.