Question: Question 11 (Ch6) When sequencing project activities in the schedule, you should ensure a. There always are scheduled dates for specific milestones b. Every activity

Question 11 (Ch6) When sequencing project
Question 11 (Ch6) When sequencing project activities in the schedule, you should ensure a. There always are scheduled dates for specific milestones b. Every activity is connected to at least one predecessor and at least one successor c. Lead or lag time should be used in each schedule d. Necessary sequencing of events may be described by the activity attributes