Question: Question 11 The program manager has come to the project manager asking for help with a bid for his newest project. You want to protect
Question 11
The program manager has come to the project manager asking for help with a bid for his newest project. You want to protect your company from financial risk, and you have limited scope definition. What is the BEST type of contract to choose?
| T&M | ||
| CPPC | ||
| Fixed Price | ||
| CPFF |