Question: Question 12. Consider you are a project engineer and need to purchase a computer-server system for your agency. You have two options, as outlined in

Question 12. Consider you are a project engineer and need to purchase a computer-server system for your agency. You have two options, as outlined in table below. Assume the annual interest rate is 6 percent. Using three different methods: Annual Cos, "Present Worth", and "Future Worth" methods, compare two systems and provide a recommendation of which system would cost less. Write all step-by-step solutions. If you provide just correct final answers, you will get only 10 percent credit of this question. (9 Points) Costs Initial Cost ($) Maintenance & Operating Cost ($/year) Salvage value ($ after 5 years) System 1 100,000 4,000 18,000 System 2 65,000 8,000 5,000