Question: Question 13 (1 point) A project has been chartered, and it now needs to done more quickly but at the same performance level. What effect
Question 13 (1 point)
A project has been chartered, and it now needs to done more quickly but at the same performance level. What effect will this have?
Question 13 options:
| A) a. The cost will increase | |
| B) b. The cost will decrease | |
| C) c. More personnel will need to be added | |
| D) d. The duration of tasks on the critical path can be held constant |