Question: Question 13. Part 1-9. Roger Ginde is developing a program in supply chain management certification for managers. Ginde has listed a number of activities that
Question 13. Part 1-9.
Roger Ginde is developing a program in supply chain management certification for managers. Ginde has listed a number of activities that must be completed before a training program of this nature could be conducted. The activities, immediate predecessors, and times appear in the accompanying table Activity Immediate Predecessor(s) Time (days) A 10 5 C D B E AD F G E. F This exercise contains only parts b, c, and d b) The critical activities for the leadership training program development project are stion stion stion B 2 2 5 5 8