Question: Question 14 (1 point) Right before a project is about to start construction, the customer changes their mind and wants to add additional work. Which
Question 14 (1 point) Right before a project is about to start construction, the customer changes their mind and wants to add additional work. Which of the following actions should the Project Manager do FIRST? Meet with customer to persuade them to cancel the additional work Determine the impact upon the project critical path Meet with the customer to understand the additional work Discuss the potential impact with the Project Sponsor and prepare to defend the delay to Senior Management Ouestion 15 nointi)