Question: Question 25 (1 point) Right before a project is about to start construction, the customer changes their mind and wants to add additional work. Which

Question 25 (1 point) Right before a project is
Question 25 (1 point) Right before a project is about to start construction, the customer changes their mind and wants to add additional work. Which of the following actions should the Project Manager do FIRST? Determine the impact upon the project critical path Discuss the potential impact with the Project Sponsor and prepare to defend the delay to Senior Management Meet with customer to persuade them to cancel the additional work Meet with the customer to understand the additional work