Question 14 The Earned Value at a specified time t represents: O A. The amount budgeted for project work as of timet O B. How much physical work has actually been accomplished and the amount originally budgeted for that work O C. Project actual expenditures as of timet O D. How much it will cost, according to the budget, to complete the project