Question: Question 15 3 pts The option to wait: 1. may be of minimal value if a project is dependent upon rapidly changing technology. 11. is

 Question 15 3 pts The option to wait: 1. may be

Question 15 3 pts The option to wait: 1. may be of minimal value if a project is dependent upon rapidly changing technology. 11. is partially dependent upon the discount rate applied to the project being evaluated. III. has a value equal to the NPV of a project if it is started at a later date IV is related to Investment timing decision - deciding when to take a project o I and III only II and IV only I and II only 0 II, III, and IV only o III, and IV only 6 pts Question 16