Question: Question 3 (3.03 points) Saved What would be the change in Average Tardiness if you performed the following five tasks using Earliest Delivery Date instead

Question 3 (3.03 points) Saved What would be the change in Average Tardiness if you performed the following five tasks using Earliest Delivery Date instead of completing them in the current sequence? Job B OOO Processing Time Days Due from Today 16 22 21 30 22 36 14 28 10 18 Lowers average tardiness by 7.0 B M Lowers average tardiness by 9.0 @L Lowers average tardiness by 11.6 AL lowers average tardiness by 6.6 lowers averare tandiness by 7.2